The first thing to understand during decoration is what are the decoration steps? What is the process of decoration? What is the order of decoration?
Let’s talk about the details of each decoration process in detail. It’s a bit long. It is recommended to click to save it first~
1. Early demand confirmation (1-2 weeks)
Specific confirmation:
1. How much money are you prepared to spend on decoration→Decoration budget
2. How much energy should be invested→Find a decoration company to choose clear package, half package or full package
3. What kind of home do you want to pretend to be→ Decoration style and needs 1. Determine the decoration budget
How to budget? Generally, 20% is reserved in the total budget to ensure that subsequent decoration will not exceed the budget due to various additions. The next budget is mainly divided into half-package of hard decoration, main materials, household appliances, and soft decoration Four parts, the reference distribution ratio is hard decoration: furniture and appliances: soft decoration 4:4:2 (Generally, decoration companies will provide budget tables for main materials of hard decoration) The first step is to list the project materials of each link in order, the second step is to fill in the found market prices into the form, the third step is to make reasonable increases and decreases in the budget according to the proportion, and then give everyone a budget table for reference (coordinates in Shenzhen , 87 square meters budget 35w):
2. Select clear package, half package, full package
The difference between these three decoration methods:
Clear package:It saves money but consumes a lot of energy. You have to buy the main and auxiliary materials yourself. The workers are only responsible for the work, and you have to go to the market for a few nailsHalf pack:It is cost-effective and is the choice of most people. You buy the main materials such as doors, windows, and ceramic tiles yourself, and the builder provides auxiliary materials such as sand, cement, and labor
All inclusive:Suitable for homeowners with sufficient budget but no time and energy. The main materials, auxiliary materials, and workers are all handled by the construction party, but be sure to allow the construction Please indicate the main material
3. Decoration style
The key point is to read more cases before installation, such as the more popular Nordic style, Japanese log style, modern black and white, etc., and be careful to avoid installation. Halfway through, I found something I like more. Here are some popular styles for reference:
② Confirm the requirements After deciding on the decoration style, the color It’s worth it. If you want to live comfortably, you have to adapt to your own living habits. At this time, you need a decoration demand list, such as how many people are in the family and how many people will be in the future…
4. Find a designer
Three common price ranges: The first type: online designers with 0-100 yuan. They will not go to the site to actually measure the room. They will produce a floor plan, renderings and layout based on the video and floor plans. 3D renderings can meet basic design needs
The second type: 100-200 yuan for designers. This price can meet the requirements of most homeowners. After all, the pure design fee is 20,000 yuan based on 100 square meters. We will provide room measurements, inquire about decoration needs, and also produce some exclusive designs based on needs, from demand tables, budget tables to floor plans, and a full set of renderings.
When looking for a designer, pay attention to two points: be sure You must be able to chat with the designer and be satisfied with the design work with real photos. Note: It depends on whether the designer and the construction team are together. If they are found separately, it must be stated in the contract at least how many times the designer must visit the construction site (key node acceptance) and how many times the design drawing must be modified at least…
Designers with a RMB 500 and above are relatively high-end, and will also have certain requirements for the decoration budget, which is generally upwards of RMB 3,000 per square meter.
After the designer reads the floor plan, he will Two or three sets of relatively innovative design plans can be customized, and the entire set of design drawings will be completed with more professional tools. For example, 3d max for renderings is the most basic
Preparatory work is the most important, it determines what your new home will look like in the future? How much will it cost to decorate?
We have prepared a decoration artifact for you!
Complete online design in 10 seconds, intelligently generated according to your needs Home renderings~
Complete online intelligent design in 10 seconds, immersive experience 3D panoramic space
2. Construction preparation stage (2-3 weeks)
1. House inspection: Check in detail whether the space and details in the house are damaged, and whether they meet the acceptance standards; if you are inexperienced, you can find a supervisor to conduct a special house inspection, which costs two Three hundred, including home inspection and repair and acceptance services
2. Choose a decoration company or construction team to measure the room and compare the quotes of 2-3 companies. The one with the lowest price is not the best. It depends on the responsibility of the foreman and the construction site under construction span>
3. Determine the decoration method: clear package, half package, full package
4. Communicate requirements with designers
5. Decide whether to install central air conditioning, fresh air, floor heating and water and electricity. You need to order in advance
6. Finalize Type of basin Before running water and electricity, determine whether the basin should be wall- or floor-drained
7. Determine the number of showers, bathtubs, toilets, lamps, switches and sockets. Before water and electricity, the location and quantity must be determined
8. Determine the decoration plan Finalize the production plan with the designer or decoration company
9. Whole house water purification system pre-filter + central water purifier + direct drinking machine + pipeline machine
10. Set a rough total budget to determine the total cost of decoration, and break it down into each small item
11. Confirm the decoration drawings Confirm the drawings with the designer or decoration company: floor plan, wall reconstruction drawing, floor material drawing, socket switch, etc.
12. Confirm the decoration contract and sign the contract with the decoration company or construction team. Pay attention to avoid adding items and omitting details. You can spend several hundred to find an accompanying signer to accompany the signing
13. Apply for gas meter installation and make an appointment for 10-15 days before on-site installation
14. Complete the decoration procedures (3-5 working days)
① Real estate certificate, the original and front pages must be photographed, the front and back of the owner’s ID card, the original floor plan, wall modification plan, construction drawings, and electrician’s certificate , decoration company qualifications
② Call your neighbors in advance Good greeting (during wall knocking construction, the noise and vibration will be relatively large, so as to avoid affecting the lives of the surrounding neighbors)
三, demolition and modification stage(2-3 weeks)
1. Material arrival and acceptance (half day)
2. Demolition and modification briefing (half day) Reconfirm the location of knocking on the wall and explain the technical solution to the workers
3. Main bodyDemolition and modification (2-5 days) ① Do not knock on the load-bearing wall ② Do not knock too hard ③ If the owner does not have time to be present, you need to explain clearly the wall to be knocked, and you can draw it with chalk to avoid the master knocking wrong
4. Build a new wall (2-5 days) ① Remember to use lightweight bricks, and remember to hang a net after finishing ② The wall cannot be built in one day, the bricks are not completely solidified, the weight is too heavy, and it is easy to The wall sinks and cracks appear ③ If there is a wall-mounted cabinet or washing machine, it needs to be reinforced. 5. Doors and windows are removed and modified (1-2 weeks) It is not a must-do, but please protect the structure of the house from damage and reinforce it
6. Measure the fresh air and central air conditioning points (about one week) ① The fresh air cabinet type machine can be installed simultaneously with the furniture. ② Generally, after the water and electricity are completed and installed, this node will come to see the on-site measurement after demolition, and then come up with a planning plan
7. Measure the cabinet size for the first time; other customizations can be made by appointment (1 day) ①The kitchen water and electricity diagram is provided by the cabinet company, and you must obtain the kitchen water and electricity diagram before the disassembly and modification are completed; ②Customized measurements such as bathroom cabinets and shower rooms can be made by appointment
8. Cleaning up garbage (half day)
9. Book security doors and windows (half a month to a month in advance)
10. Book kitchen and bathroom equipment Order kitchen and bathroom supplies as early as possible, mainly for accurate size, and also to allow yourself to judge from another angle whether the number of sockets and the height of the sockets are correct. To avoid subsequent regrets, please do not move all the products you have ordered back home at this time, as they will be very inconvenient
4. Hydropower transformation (2-3 weeks)
1. Water and electricity information and positioning (1 day) Gather the central water purifier manufacturers for cabinets, air conditioners, floor heating, and integrated stoves to determine the usage and installation locations, and conduct water and electricity positioning together. The manufacturers and plumbers will conduct water and electricity briefings (mark them on the wall with chalk, with pictures and serial numbers)
2. Circuit modification (1-2 weeks) After completing the circuit, Be sure to ask the builder for a circuit layout diagram, to prevent the wires from being damaged during future maintenance or when driving nails into the wall.
3. Waterway Transformation (1-2 weeks)
① Don’t go to the topWalking on the ground
②Be careful to protect the drain before construction
③After completing the renovation, remember to do a water pipe pressure test
④Avoid horizontal grooves, especially in load-bearing walls
4. Water and electricity acceptance (1 day) Check whether there are dead lines in the pipes, whether the leakage switch is installed correctly, whether the lamps are lit and the lamp control performance is good.
5. Install water retaining strips (half a day) If you install it early, you can completely seal the bottom of the waterproof strip. When doing waterproofing, you can also brush the bottom of the rain-proof strip together, so that you can better avoid water
6. Installation of floor heating (3-7 days) Floor heating is completed after wall renovation and water and electricity renovation It is most suitable to lay it later. After the floor heating is backfilled, water and electricity trenching cannot be carried out, otherwise the floor heating will be damaged, and the wall cannot be modified.
7. Seal and install windows (1 day) The window frame must be installed, otherwise the bricklayer will not be able to close it when laying bricks
8. Install fresh air and central air conditioning (1-2 days)
① According to the measurement plan prepared in the early stage, after the completion of water and electricity, fresh air and central air conditioning can be installed ② Fresh air and central air conditioning should be installed at the same time as much as possible
9. Purchase cement, mortar, ceramic tiles, edge strips, stone and other ceramic tiles in advance before decoration, and make an appointment with the delivery time. They will be used on the first day of the tiler work
10. Buy a floor drain When laying ceramic tiles, ask the tiler to install the floor drain
11 .Waterproof treatment (1-2 days)
① Apply thinly and brush frequently, 2-3 times horizontally and vertically. No blisters or bubbles should appear. ② The waterproofing must be at least 1.8m high
12. Bathroom water storage test (more than 2 days) not less than 48 hours, and notify Residents downstairs, check with the property ownerIf the waterproofing is not done well, it will be inconvenient to live in and troublesome to rectify, so it is best to ask more
5. Bricklaying Stage
1. For enclosed balconies, report to the property management company in advance. It is recommended to use broken bridge aluminum for window sealing. It is safer to look for the ccc mark on the glass
2. Ground leveling
3. Flatten the wall
4. Fill the holes dug during demolition and water and electricity construction
5. Make floor drains and threshold stones
6. Pre- Arrange tiles
① If there is special paving, arrange the tiles in advance
②Pave ceramic tiles, floor tiles, and skirting boards
③Remember to reserve 3-5 more tiles to prevent tile damage
p>
7. Ceramic tile acceptance ① is level, ② is flatness, ③ is hollow
8. Door and window caulking
9. Guarantee ① Remember to reserve access openings for future pipeline repairs ② Those who are very concerned about noise It is also necessary to add noise insulation cotton
10. Install security doors
11. Install bathtubs, wash basins, and squat toilets
①The bathtub needs to be moved aside by the tiler ②The squatting toilet needs to be done before laying the tiles
12. Install window sill stone
13. Gas pipeline rerouting (1 day)
① After laying the tiles, before installing the cabinets, reroute the gas pipeline ② Note that some areas do not allow pipeline rerouting
14. Purchase the materials needed for woodworking Prepare wood, veneer, etc.
15. Buy door (finished product)
①General door production cycle is long (30-50 days), remember to make it in advance
②After the door size is determined, door accessories such as door locks, door suckers and other accessories can also be purchased together
③Order wooden flooring (at least 10 days in advance) to be used in the next carpentry stage span>
16. Measurement Kitchen and bathroom ceilingOpening position and aperture cabinets, customized furniture ruler, confirm sink size
6. Carpentry stage (1- 2 weeks)
1. Beautiful sewing
2. Carpentry materials arrival and acceptance (half day) After entering the site, the wood and veneer panels should be stored in a ventilated and dry room, and pay attention to moisture-proofing 3. Ceiling construction
4. Decorative panel installation On-site carpentry production, such as wardrobes, entryway cabinets, bookcases
5. Install curtain box
6. Door installation ① Indoor doors are usually installed after painting ②But if the invisible door is made by on-site carpentry, it needs to be done on-site at this stage
7. Wooden floor installation requires waiting for the ceiling, interior walls, doors and windows to be installed before proceeding
8. Woodworking Acceptance inspection (half day) Pay attention to details such as gaps, structures, damage, corners, parquets, nail holes, etc.
9. Install water heater and wall-mounted shower ① When draining electricity, the location of the water heater must be determined in advance ② When installing the water heater, install the water heater first and then contact the ceiling Manufacturers and ceiling masters will wrap up the water heater when lifting the ceiling
10. Purchase lamps
11. Buy wall paint and wallpaper in advance (15-20 days in advance)
7. Painting stage (1-2 weeks)
1. Admission and acceptance of paint materials ① Pay attention to whether the materials are environmentally friendly, packaging and production date ② Smell whether the latex paint has a pungent smell
2. Treat the base layer of the wall to ensure that there is no floating dust or soil on the wall as much as possible 3. Putty scraping ① scrape at least twice ② The interval between scraping and scraping of borderless putty should be more than 2 hours, but some putties cannot be scraped for such a long time
4. Apply latex primer Just apply the latex primer once, follow the principle of one base and two sides, and paint in spatial order
5. Paste Wallpaper and topcoat need to be applied more than twice, with an interval of more than 2-4 hours
6. Purchase remaining building materials in advance, such as switches and sockets, bathroom partitions, bathroom heaters, etc. It is best to make a list and sort by space area. Hardware that has not been purchased and needs to be installed Product
8. Installation phase (one week+)
1. Kitchen and bathroom integrated ceiling installation
2. Cabinets + Range hood installation (base cabinet)
3. Installation of curtain rods and clothes drying racks
4. Switch socket installation
5. Lighting installation
6. Customized cabinet installation
7. Toilet installation
8. Pass , Window cover installation
9. Touch up paint after installation (1 day)
10. Land reclamation and cleaning (1-2 days) After the hard decoration is completed, land reclamation and cleaning should be carried out before the furniture and home appliances enter the site. It is best to complete it before the curtains are installed
9. Soft decoration stage
Furniture, curtains, screens, all appliances, decorations In principle, enter the market in order of large items first and then small items.
Decorations can even be added slowly after moving in.
10. Preparation for move-in stage
1. Ventilate to remove formaldehyde (at least three months)
2. Open TV network (1-2 days)
3. Turn on gas (half day)