Decoration is similar to learning bicycles. You can read the decoration strategy thousands of times online, but you will inevitably fall if you get it yourself. Therefore, the purpose of our strategy is not to understand how to operate each link, but to understand common sense and establish knowledge index, and to prevent and remedy in advance where it is easy to fall into pitfalls.
Today, I will explain the entire process of decoration and precautions for you. After reading it, novices will not fully understand the way of decoration companies. At least they know where there are easy things to be tricky in the decoration and how to avoid pitfalls. They will also have more direction and confidence when communicating with decoration companies!
1. Preparation
● Decoration steps
①Confirm the half-packing and repair (1-2 days)
②Confirm the design plan (3 days)
③Change the total budget (4 days)
④Confirm the electrical appliance model/size (10-15 days)
⑤Renovation procedures (2 days)
● Notes
① Confirm the materials before the construction drawings, otherwise the selection of materials after construction will affect the construction process and quotation.
② Before starting construction, print a decoration notice at the door of the unit and inform the neighbors that they want to decorate.
③ If you have half a package, just look for a local small decoration company; if you have all packages, you have to find a large decoration company to examine their main material supply capabilities.
④ If you add one to the contract, the final decoration cost will not exceed 5% of the budget, and the excess will be borne by some decoration companies.
● The main materials that the owner needs to purchase
Whole house water purification, temporary toilets, sewer covers, central air conditioning, floor heating, fresh air, anti-theft doors, anti-theft windows
The most important thing in the preliminary preparation process is to find a reliable decoration company. Brother Wen said the \”secret\” of an industry: some decoration companies do not support their own workers, and after signing the contract, they will decorate the cooperative construction team. In other words, no matter whether you are looking for a decoration company or a construction team, it is possible that the same group of people are working.
Is it possible to directly contact the construction team? No, the difference is quite big. The decoration company will have construction standards to restrict workers. Even if the same group of people work, the decoration company can ensure that your construction quality is better than that of the construction team and the process is more standardized.
Although the construction team is about 15%-20% cheaper than the decoration company\’s quotation, don\’t think about after-sales service or something. Although decoration companies are expensive,There are a series of quality assurances and after-sales guarantees. For example, hidden projects such as water and electricity generally have a 5-year warranty and a 2-year warranty for surface projects.
2. Demolition and modification stage
● Decoration steps
① Dismantling and restructuring briefing (half-day)
② Knocking the wall and shoveling the wall (2-5 days)
③ Demolition and new construction (2-5 days)
④ Garbage removal (half-day)
④ Garbage removal (half-day)
⑤Initial measurement of cabinet size (1 day)
● Notes
①In this stage, the focus should be on good protection of floor drains to prevent construction waste from falling into the sewer and causing blockage.
②The connection between new and old walls should be carried out to prevent hollowing and cracking in the later stage
③Confirm that the wall is removed to the cement mortar layer or the red brick layer to avoid additional items
④ Garbage removal is a common missed item. Check with the decoration company in advance whether it is included. If it is not included, it will save money by handling it yourself.
● Main materials that need to be purchased by the owner
Sanitary ware, embedded refrigerator, range hood, gas stove, wall sanitary ware, and bath partition
IV. Brickworking stage
● Decoration steps
① Brickworking briefing (half-day)
② Turbo water treatment (2-3 days)
③ Water closing experiment (2 days)
④ Install wall tiles, floor drains, and door stones (5-6 days)
⑤ Brickwork acceptance (1 day)
● Notes
① Before doing waterproofing, you must say hello to the neighbors downstairs. It is best to go downstairs to see if there is a leak.
②When laying tiles on kitchen and bathrooms, prepare a flue check valve.
③ Find good wall and floor tiles and beautiful jointsThe manufacturer of agent and windowsill stone starts to make reservations.
⑤ Whether to install door stones will affect the early leveling work. The method of replacing door stones with extremely narrow strips requires no level height difference on the ground.
● Main materials that the owner needs to purchase
Interior doors, wooden floors, protective films, latex paint (select to purchase)
V. Woodworking/painting stage
● Renovation steps
① Ceiling construction (2-3 days)
② Install curtain boxes (1 day)
③ Make cabinets on site (2 days)
④ Woodworking acceptance (3-4 days)
⑤ Scrape putty (2-3 days)
⑤ Scrape putty (2-3 days)
④ Carpentry acceptance (3-4 days)
⑤ Scrape putty (2-3 days)
⑥ Brush latex paint (1-2 days)
● Notes
① After the materials are entered, check whether the model and manufacturer are consistent with the contract to prevent inferior products from being used as good products.
② When making the ceiling corner, you must cut the entire board into a 7-shaped shape.You can splice two boards, otherwise it will easily crack if you apply latex paint.
③ The spacing between the main keel is <1000mm, the spacing between the secondary keel is <400mm, the spacing between the hanging points is <1000mm, and the ceiling width exceeds 700mm.
The oil worker process is also recommended to go to the acceptance in person. Some workers are perfunctory if you don’t focus on working, and cutting corners is common.
VI. Installation stage</spanning room hardware</spanning room, custom cabinets, etc.
After all this, the decoration is basically over. All the family members who have seen this, please give me some tips to give me some advice. Thank you~
Lastly, let me talk about it, it is also important to plan the selection and entry time of materials. Not only do you need to understand the name and function of the materials, but also know the timing of their purchase. Buying too early will take up space, and buying too late will affect the construction progress and delay the entire decoration plan.